Post-Tensioned Slab Formwork
Aluminum beam formwork systems engineered for post-tensioned concrete slab construction. Joist layouts provide tendon clearance, drophead technology enables 3-day stripping, and reshoring supports slabs during stressing operations. Optimized for residential and commercial PT projects across Ontario.
Day Strip
Strip Strength
Compatible
Post-Tensioning Formwork Advantages
Aluminum beam systems designed specifically for the unique requirements of post-tensioned concrete construction.
Tendon Clearance
Joist spacing and layout coordinated with PT strand locations. Tendons pass between joists in open space. No contact between formwork and ducts. Prevents damage to plastic sheathing during concrete placement.
Early Strip Capability
Strip formwork at 3 days when slab reaches 2,500 psi (17 MPa). This strength is sufficient for PT stressing operations which typically occur days 3-5. Aluminum dropheads release joists while reshoring remains.
Drophead Technology
Aluminum dropheads connect joists to shores. After 3-day strip, dropheads lower 150 mm to release formwork. Reshoring remains supporting slab during tendon stressing and until full strength. Critical for PT safety.
Strand Layout Accommodation
Formwork layouts account for PT strand banding (concentrated tendons at column strips) and distributed tendons in middle strips. Joist spacing widens at middle strips, tightens at column strips to clear tendon groups.
Deflection Control
PT slabs are typically thinner than conventional slabs (200-250 mm vs 250-300 mm). Formwork must limit deflection to prevent cracking before stressing. Aluminum beams sized for L/360 deflection under wet concrete load.
Reusability
200+ reuses typical for aluminum PT formwork. Coordinate joist layout with PT engineer so same formwork pattern repeats on each floor. Standardized layouts maximize equipment reuse across multiple levels.
PT Slab Formwork Cross-Section
Aluminum joist layout coordinated with post-tensioning strand locations for clearance and support.
- Column strip coordination — Banded tendons (4-8 strands) at column centerlines require 900-1200 mm joist spacing to clear tendon bundles, with larger beam sizes for wider spacing.
- Middle strip layout — Distributed single-strand tendons at 600-900 mm spacing with standard 6.5" aluminum joists at 450-600 mm intervals positioned between tendon paths.
- Thinner slab advantage — PT slabs at 200-250 mm (8-10") thickness reduce dead load compared to conventional 250-300 mm slabs, with draped tendon profiles requiring variable vertical clearance in formwork.
- Pre-construction coordination — Formwork supplier overlays joist layout on PT strand drawings, resolving all conflicts in a pre-construction meeting before slab pour to ensure zero tendon contact.
PT vs Conventional Slab Forming
Formwork considerations and cycle time comparison for post-tensioned versus conventionally reinforced concrete slabs.
| Specification | Factor | PT Slab Formwork | Conventional Slab | Difference |
|---|---|---|---|---|
| Slab Thickness | 225 mm (9") | 275 mm (11") | PT: 18% thinner | |
| Concrete Volume | 225 m³ | 275 m³ | PT: 50 m³ savings | |
| Strip Timing | Day 3 @ 2,500 psi | Day 7-10 @ full cure | PT: strip 4-7 days earlier | |
| Formwork Complexity | Coordinated joist layout | Standard joist spacing | PT: more coordination required | |
| Reshoring Duration | 10-14 days (through stressing) | 7-10 days (until cure) | PT: 3-4 days longer reshoring | |
| Floor Cycle Time | 5-7 days | 7-10 days | PT: 30% faster cycle | |
| Total Slab Cost | $165/m² ($15.3/ft²) | $180/m² ($16.7/ft²) | PT: 8% cheaper overall | |
| Structural Span | 10-12 m (33-40 ft) | 8-9 m (26-30 ft) | PT: 25% longer spans |
Post-Tensioned Slab Construction Process
Typical 7-day cycle from formwork setup through tendon stressing. Day 0 is concrete placement.
- 1
Formwork and Rebar (Day -2 to 0)
Set aluminum formwork with joists coordinated to PT layout. Install bottom rebar mat and chairs. PT crew places tendon ducts and anchors per shop drawings. Install top rebar. Pre-pour inspection. Pour concrete day 0.
- 2
Concrete Curing (Day 1-3)
Concrete cures to 2,500 psi minimum at 72 hours. Take field cylinders at pour and test at 3 days. Cold weather or low-cement mixes may require 4 days to reach strength. Hot weather accelerates to 2 days.
- 3
Strip Formwork (Day 3)
At 2,500 psi, lower aluminum dropheads to release joists. Remove beams, joists, and plywood deck. Reshoring remains in place supporting slab. Formwork ready to reset at next level. 6-8 hours with 4-person crew.
- 4
Tendon Stressing (Day 3-5)
PT crew stresses tendons using hydraulic jacks at anchor pockets. Strand elongation monitored and recorded per engineering. Stressing introduces compression into slab. Cut and grout pockets after stressing complete.
PT Slab Formwork FAQs
Common questions about formwork systems for post-tensioned concrete slab construction.
Related Solutions
Elevated Slab Forming
Multi-story formwork systems with drophead technology for conventional reinforced concrete slabs.
Slab Formwork Tables
Crane-lifted flying form tables for high-rise PT construction with repetitive floor plates.
High-Rise Reshoring
Multi-level reshoring systems for safe load transfer during PT stressing and concrete curing.
PT Formwork Coordination
Avema's engineering team will coordinate formwork layouts with your PT engineer and provide complete shop drawings for approval.